- As the yellow line’s first phase, running from Bommasandra to Central Silk Board is nearing up for the proposed opening by June 2023, we took a closer look at the progress of this stretch.There are three division of work package in the stretch are
-
Package 1 : Bommasandra - Biretana Agrahara ( 468 Cr )
Package 2 : Biretana Agrahara - Bommanahalli ( 492 Cr )
Package 3 : Bommanahalli - RV Road ( 797 Cr ) - All civil works are completed over 90% with all plastering, cladding, tiling, Rails and electrical systems, and station booth system in expedited progress. These stations are constructed in partnership with Infosys, and there have been proposals to extend this line to Hosur( Tamil Nadu’s Responsibility ). All pictures for the current progress is taken on Dec 15th 2022.