Status on Commissioning of Reach-5 Line (Yellow Line)from RV Road to Bommasandra
- Oct 18th, 2024
Civil / System works have been substantially completed.
Commissioning Plan
► Testing with Proto-Type Train is under progress
► Technical sanction of Railway Board w.r.t. Traction is received
► For Signalling System and Rolling Stock are in advance stages
Rolling Stock Availability
► 3 Train Sets will be available by Nov-Dec 2024
► Commissioning of Section with Three Trains is targeted by January 2025
with the Head-way of 30 minutes
Section will be offered for CMRS Inspection in December 2024
► Further, Trains will be received from TRSL at the rate of 2 Trains per month w.e.f. March 2025 and Head-way will be reduced progressively
► All the 15 Trains sets for Reach-5 line will be available by August 2025